Water finds the weakest line in a bathroom: a corner where the membrane stops, a pipe that passes through without a seal, or a floor that falls away from the drain. These are cheap to correct before tiling and expensive afterwards.
1. Define the wet zone
Decide which floor area will regularly be wet: the shower, the area around the bath, and the zone in front of the vanity. A curbless shower looks generous, but it needs enough structural depth for the drain and the fall; if the slab cannot provide it, a low curb or a linear drain is the honest solution.
Check the door threshold at the same time. Water should not be able to run out of the bathroom under the door, especially where the adjacent floor is timber.
2. Get the falls right
A shower floor typically falls about 1-2% (10-20 mm per metre) towards the drain. A linear drain can use a single slope; a square drain needs falls from four directions, which is harder to achieve neatly with large tiles.
Set out the tile layout before the screed, because the fall and the tile format have to agree. Large-format tiles on a four-way fall produce awkward cuts; smaller tiles or a linear drain usually give a cleaner result.
Test with water before tiling. If water stands in a corner, the fall is wrong, not the tile.
3. Build a continuous waterproof layer
A paint-on or sheet membrane is only continuous if it is detailed at every junction. In a shower, carry the membrane up the walls to at least 1800 mm or to full height where the shower is open. Elsewhere, a 150 mm upstand at the floor perimeter is a common minimum.
Use the membrane manufacturer's tape and corners at internal corners, pipe entries, niches and the junction with the drain. A membrane that is cut around a pipe and sealed with silicone is not a waterproofing detail.
Where the substrate changes - for example, a lightweight block wall meeting a concrete floor - allow for movement with a bond breaker rather than locking the two together.
4. Flood-test before tiling
Once the membrane has cured, block the drain and flood the floor with about 20-30 mm of water for 24-48 hours. Mark the level, check the room below if there is one, and photograph the result. A failed test at this stage costs a day; a failed test after tiling costs a bathroom.
5. Detail niches, benches and penetrations
Slope the base of every niche slightly forward so it drains. Blocking for a bench or a wall-hung basin should be fixed before the membrane, and the membrane should run over the blocking, not around it.
Every pipe and cable entry needs a sealed collar. For a wall-hung toilet, confirm the frame, the waste route and the service access before the wall is closed.
6. Drainage and ventilation together
A bathroom needs both a working drain and an effective extractor. Check the waste pipe fall, the trap type and the access point. A bottle trap hidden behind a sealed panel is a future problem.
Size mechanical extract to the room volume and run it long enough after a shower to remove moisture. If there is a window, natural ventilation still needs a planned opening and, in humid climates, mechanical extract is usually more reliable.
7. Choose the finish for a wet floor
Slip resistance matters more on a shower floor than on a wall. Ask for the measured slip rating of the actual tile, not a general description such as "anti-slip". Smaller formats and textured surfaces generally give better grip; polished large-format tiles are a poor choice for a wet floor even when they look calm and minimal.